This site illustrates some of the items from the Scope of Work for the renovation of the three 1916 Cottages remaining in Belltown.
|
|
|
This is the
south roof of 2512. The original cut shingles are under a
few layers of roll roofing. |
|
paintedcottage-pp.JPG |
Here is the goal for the 3 Cottages, a fresh finished look. This was 1996. |
|
1916wh-pp.JPG |
This is one of the Cottages just completed, May 1916. |
|
paintedgarage-pp.JPG |
Basement and gagarge added in 1940s. |
|
P0006495-pp.JPG |
Remove painted cedar shingles installed over bevel siding from west wall and dispose. Abate original cedar bevel siding below. Remove plywood covering over exterior porch to allow abatement of porch walls. Do not abate basement door or plywood cover sheet to left of basement door. These will be disposed of after site is secured. |
|
P0006496-pp.JPG |
Remove plywood covering over windows in skirting (3 sides) to abate white paint from window trim. |
|
P0006497-pp.JPG |
Remove rotten beaded paneling from south eves. |
|
P0006501-pp.JPG |
Do abate kitchen door, 2512. Door will be refurburshed, and reinstalled. This is the ONLY remaining original door. Remove kitchen door awning and save. |
|
P0006510-pp.JPG |
Remove security screens from windows once construction fencing is installed. Abate storage shedd door and jamb. |
|
P0006511-pp.JPG |
Remove imitation brick siding, grey roll roofing and metal flashing from skirting to expose unpainted shiplap below(4 sides.) Remove covering over 2 windows in skirting to abate painted trim. Remove blue exterior stairs and set aside. Remove security screens from windows once construction fencing is installed. |
|
P0006518-pp.JPG |
Remove plywood covering over front crawlspace access to abate red paint from skirting. |
|
P0006520-pp.JPG |
Remove rotten beaded paneling from north, south & west eves. |
|
P0006521-pp.JPG |
Do not abate kitchen door, 2516. Door will be removed, patterned, have hardware removed and then disposed of. Remove kitchen door awning and save. Remove security bars from windows. Shedd on back of 2516 will be removed prior to abatement of east wall. |
[Home] [1916 Images] [Nov 2002] [Dec 2002] [Jan 2003][Feb 2003][Abatement]
Friends of the
Belltown P-Patch
a neighborhood 501(c)3 non-profit
organization
2225
First Avenue Seattle, WA 98121
206.441.770
Created by Myke
Woodwell on his trusty Powerbook over Saturday morning coffee.
Images
by Myke JWoodwell ©2001
Myke
Woodwell / mykejw@speakeasy.org